A long cold-storage warehouse with steel frame and loading docks at dusk

INDUSTRIAL · CHATEAU · 2024

(ALLEGHENY

COLD STORAGE)

210,000 sq ft of temperature-controlled warehouse: steel trusses, insulated panel walls and 24 dock doors, delivered design-build.

CLIENT

Allegheny Foods Logistics

VALUE

$22M

SIZE

210,000 sq ft

SCHEDULE

14 months, on the day

STEEL

640 tons, erected in-house

SAFETY

0 lost-time incidents

FOURTEEN MONTHS FROM FIELD TO FREEZER.

One contract covered civil, steel, insulated panels and refrigeration. Our crane crew set the roof trusses in eleven working days, and the panel installers closed the shell before the first frost so the slab could cure under cover.

The finished cold-storage hall with steel trusses, insulated panel walls and a forklift in the aisle
The finished cold-storage hall with steel trusses, insulated panel walls and a forklift in the aisle
A crane lifting a roof truss over the brick shell while the crew guides it from below

BEFORE / AFTER.

Drag the torch to see this site before and after the build.

A long cold-storage warehouse with steel frame and loading docks at dusk
The gutted brick warehouse hall before the rebuild, with a worker on a scissor lift among the scaffolding

BEFORE

HANDED OVER

© 2026 Ironlath Builders · PA License #PA071442

LICENSED IN PA, OH, WV

© 2026 Ironlath Builders · PA License #PA071442

LICENSED IN PA, OH, WV

© 2026 Ironlath Builders · PA License #PA071442

LICENSED IN PA, OH, WV

000
IRONLATH

Create a free website with Framer, the website builder loved by startups, designers and agencies.